Calculators for what a circuit supplies and what it carries: kVA, kW and amps on single- and three-phase systems, line-to-neutral voltage and whether a meter reading is in range, Ohm's law, the service a house needs, and what a load costs to run. Each shows how it's calculated.
kVA · kW · ampsTransformer, generator and UPS sizing. Three-phase uses line-to-line volts.
Line ↔ neutral voltageThree-phase systems: line-to-neutral = line-to-line ÷ √3. Check a meter reading against the limits for its nominal voltage.
Ohm's lawEnter any two of volts, amps, ohms and watts to get the other two, and what a heater gives on another voltage.
House service sizeThe calculated load of a single dwelling and the service it needs, by the NEC optional method or CEC Rule 8-200.
Energy costWhat a load costs to run, and what a retrofit saves.
Quick answers
- kVA · kW · amps: 75 kVA at 208 V three-phase → Line current: 208.2 A
- Line ↔ neutral voltage: 208 V line-to-line → Line-to-neutral: 120.1 V
- Ohm's law: 120 V and 1,500 W → Amps: 12.5 A
- House service size: 1,500 ft² by the NEC optional method → Service size, at least: 110 A
- Energy cost: 1,500 W for 8 h a day, 365 days a year → Per year: $657.00